“M6 Metro Line. 1 Mai – Otopeni, Bucharest International Airport Rail Access Link Project (Metro Line 6. 1 Mai – Otopeni)” is a project of significant local relevance with a considerable regional and international impact.
One of the strategic financiers of the M6 Project is the Japan International Cooperation Agency – JICA, whose delegation made several official visits to Bucharest on Friday, 20th September 2024.
JICA investors met with representatives from the Ministry of Transport and Infrastructure, including Mr. Ionuț Săvoiu, State Secretary, and Ms. Mariana Ioniță, Secretary General, as well as representatives from the Ministry of Finance, Metrorex, under the coordination of Ms. Mariana Miclăuș, General Director, and from the Project Supervisor, International joint venture consisting of PADECO Co., Ltd. – ORIENTAL CONSULTANTS GLOBAL Co., Ltd. – METROUL S.A.
The meeting discussed the project’s progress and reviewed the current state of its implementation.
The JICA delegation, led by Mr. Kei Toyama, Director General of the Europe Division, Department for the Middle East and Europe, accompanied by representatives from Metrorex, the Supervisor, and the Constructors, visited the sites of future stations on M6 Metro Line, Gara Băneasa and Tokyo.
The constructor of the South Section, designated for the works on the 1 Mai – Tokyo section, presented the progress made on the two future stations visited.
The progress of the works, recorded in the first half of September 2024 in the M6 Metro Line South Section Site Journal, is outlined below:
Video: https://youtu.be/3F4kYz828_I
- For the future Tokyo metro station, 270 metres of guide beam have been installed, along with 47 diaphragm wall panels and 358 plastic piles for soil reinforcement.
- Works have commenced on the bored piles for the future interstation Aeroport Băneasa – Tokyo; out of a total of 180, 23 piles have been completed.
- At the future Aeroport Băneasa station, 263 metres of guide beam have been installed, along with 24 diaphragm wall panels and 160 plastic piles.
- For the future Gara Băneasa station, 35 diaphragm wall panels and 6 plastic wall panels have been completed for the TBM (tunnel boring machine) exit.
- For the future interstation Piața Montreal – Gara Băneasa, 181 bored piles have been completed.
- At the future Piața Montreal station, 191 metres of guide beam and 23 diaphragm wall panels have been installed.
- At the future Expoziției station, 544 metres of guide beam and 45 diaphragm wall panels have been installed, and for the electrical station, 121 metres of guide beam and 17 diaphragm wall panels.
- For the future interstation Pajura – Expoziției, more than 190 piles have been installed.
- At the future Pajura station, 459 metres of guide beam and 10 diaphragm wall panels have been completed. At Access A, 42 bored piles have been installed.
- At the future interstation 1 Mai – Pajura, 32 bored piles have been completed.
- At the future 1 Mai metro station, site organisation works and utility relocation are being carried out.