It is located near the west access of the Romexpo Exhibition Complex. The station has a total length of 288 m, of which 142.0 m in the maneuvering area at the north end, and a width of max. 24.4 m.

Structural monitoring

Measurements to date confirm that the integrity of the buildings is within normal parameters.

Traffic restrictions

  • Announcement of September 13, 2024: link

Status of works

  • September 2025: 171 piles for Access A, over 36,000 cubic meters excavated and over 6,500 cubic meters concreted. Implementation percentage of civil works: 63%.
  • August 2025: over 23,000 cubic meters excavated and 4,900 cubic meters concreted. Implementation percentage of civil works: 59%.
  • July 2025: 102 diaphragm wall panels, 43 barrettes, 699 plastic piles, 3,866 cubic meters of concrete poured. Implementation percentage of civil works: 56.8%.
  • June 2025: 693 m guide beam, 100 diaphragm wall panels out of 102, 9 plastic diaphragm walls, 591 plastic piles, 21,927 cubic meters excavated and 2,163 cubic meters concrete poured. Implementation percentage of Civil Works: 55%.
  • May 2025: 677 m guide beam, 93 diaphragm wall panels out of 102, 35 barrettes out of 43, 112 piles for Access A, 186 piles for Access B, 6 plastic diaphragm walls, 474 plastic piles out of 691; 11,853 cubic meters excavated, 2,076 cubic meters concrete poured;
  • April 2025: 644 m guide beam, 85 diaphragm wall panels out of 102, 62 piles for Access A, 167 piles for Access B, 118 piles for Access C, 23 plastic piles, 8,497 cubic meters excavated, 1,620 cubic meters concrete poured;
  • March 2025: 563 m guide beam out of 625, 76 diaphragm wall panels out of 102, 35 barrettes, 106 piles for Access B, 6 plastic diaphragm wall panels, 4,840 cubic meters excavated and 1050 cubic meters concrete poured;
  • February 2025: 75 diaphragm wall panels out of 102, 35 barrettes out of 43 and 62 piles for Access B;
  • January 2025: 74 diaphragm wall panels out of 102, 27 barrettes out of 43, 118 piles for Access C, 6 piles for Access B;
  • December 2024: 551 m guide beam, 72 diaphragm wall panels, 15 barrettes and 6 plastic piles; for Access C – 64 piles for the electrical station, 121m guide beam and 20 diaphragm wall panels;
  • November 2024: 68 diaphragm wall panels, 11 barrettes and 34 piles for Access C;
  • Octomber 2024: 56 diaphragm wall panels, 6 barrettes and 6 plastic piles;
  • September 2024: 551 m guide beam, 45 diaphragm wall panels, 532 piles for Accesses A, B and C and 5 plastic piles; for the electrical station 121m guide beam and 20 diaphragm wall panels were made;
  • August 2024: 540 m guide beam, 36 diaphragm wall panels for the station and 15 diaphragm wall panels for the electrical station;
  • July 2024: We have completed 540 m of guide beam out of a total of 630m, 31 diaphragm wall panels (out of 122) for the station and 8 diaphragm wall panels (out of 20) for the electrical station. Utility diversion works are ongoing. Regarding the upcoming Expoziției – Pajura interstation, we have completed all bored piles and have commenced the excavation for the cap beams;
  • June 2024: We have completed all excavation, reinforcement, formwork and concrete pouring works for the guide beams; Regarding the upcoming Expoziției – Pajura interstation, we have completed the drilling, reinforcement and pouring works for 8 secant piles;;
  • May 2024: At the Exhibition – Montreal Square interstation, 26 pieces of fencing have been installed;
  • March 2024: Work has progressed with the preparation for the guide beams and the execution of the diaphragm wall panels; The access road and work platform have been set up at the upcoming interstation Expoziției – Pajura;
  • February 2024: We have carried out mechanized excavation works and manual digging to identify possible utility networks; we also conducted a permeability test of the soil;
The future M6 metro line will transform the daily commute into a pleasant and fast journey to important destinations within the capital and Ilfov. Stations under construction:
South Section
Pajura

Located on the northern side of the Bucharest – Constanța railway, near Băiculești Street.

Read more
EXPOZIŢIEI

Located north of the eastern entrance of Romexpo.

Read more
PIAŢA MONTREAL

It will be located on Mărăști Boulevard, adjacent to the tram and bus terminal near Piața Montreal.

Read more
GARA
BĂNEASA

Adjacent to the Bucharest – Ploiești Road, on the esplanade in front of Băneasa Station, at the intersection of Tipografilor Street, the Bucharest – Ploiești Road, and the Bucharest – Constanța railway.

Read more
AEROPORT
BĂNEASA

Adjacent to the Bucharest – Ploiești Road, north of the intersection between Aerogării Boulevard and the Bucharest – Ploiești Road

Read more
TOKYO

Adjacent to the Bucharest – Ploiești Road, near the overpass next to the Băneasa Shopping City complex.

Read more
North Section
WASHINGTON

Located adjacent to the Bucharest – Ploiești Road, near the overpass at Jandarmeriei Street.

Read more
PARIS

Located at the intersection of the Bucharest – Ploiești Road and Padina Street.

Read more










BRUXELLES

Located near the overpass at the intersection of the Bucharest – Ploiești Road and the Capital’s ring road.

Read more
OTOPENI

At the intersection of Calea Bucureștilor and 23 August Street in Otopeni.

Read more
ION I.C. BRĂTIANU

At the intersection of Calea Bucureștilor and Zborului Street in Otopeni.

Read more










AEROPORT OTOPENI

Under the roadway in front of Otopeni “Henri Coandă” International Airport, near the parking area adjacent to the Departures terminal and the exit routes from the Arrivals terminal.

Read more