Bruxelles station will be located on the east side of the Bucharest – Ploiești Road, in the north-east area of the intersection between the Bucharest – Ploiești Road and the Ring Road (D.N.C.B.). The Bruxelles station is the launch pad from which the TBMs will be launched in each of the two directions. This station will be equipped with two access points, a gallery and a parking lot in the adjacent green area. The height of the parking lot is B+Gf+1F+walkable terrace. Bruxelles station has a length of 295 m, of which 146.3 m are for the shunting area at the northern end, and has a maximum width of 28.27 m.
Current Work Status
- July 2026: Utility relocation works continued, along with the execution of the diaphragm walls for the TBM launch shaft. Structural works progress: 19%.
- June 2026: Utility relocation works continued, along with the execution of the initial structural elements – diaphragm walls, barrettes and guide beams. Structural works progress: 15%.
- April 2026: Site preparation works, utility relocations and initial works for the structure (diaphragm walls, barrettes and guide beams) were carried out. Structural works progress: 10%.
- March 2026: Mobilisation and site preparation works, utility relocations and works specific to the structure were carried out. Structural works progress: 8%.
- February 2026: Electrical and water utility relocation activities are under way, and the execution of the guide beams has reached 56%. Barrettes and diaphragm walls are being executed, and Access A stands at 2%. Structural works progress: 5%.
- January 2026: Additional quantities of work were executed, namely 130 linear meters of drilling for the deep well and approximately 1,500 kg of reinforcement for the guide beams of the diaphragm walls.
- 2025 Year in Review: https://youtu.be/ieKd0B_EEyc
- November 2025: A total of 169 linear meters of guide beams for the diaphragm walls were completed, along with 22 guide beams for the station barrettes (94.6 linear meters), with 228 m³ of soil excavated. Structural works progress: 38%.
- October 2025: Preparatory works were carried out for the excavation and support phases, including equipment mobilization and topographical verification of the site.
The future M6 metro line will transform the daily commute into a pleasant and fast journey to important destinations within the capital and Ilfov. Stations under construction:
Pajura
Located on the northern side of the Bucharest – Constanța railway, near Băiculești Street.
Read morePIAŢA MONTREAL
It will be located on Mărăști Boulevard, adjacent to the tram and bus terminal near Piața Montreal.
Read moreGARA
BĂNEASA
Adjacent to the Bucharest – Ploiești Road, on the esplanade in front of Băneasa Station, at the intersection of Tipografilor Street, the Bucharest – Ploiești Road, and the Bucharest – Constanța railway.
Read moreAEROPORT
BĂNEASA
Adjacent to the Bucharest – Ploiești Road, north of the intersection between Aerogării Boulevard and the Bucharest – Ploiești Road
Read moreWASHINGTON
Located adjacent to the Bucharest – Ploiești Road, near the overpass at Jandarmeriei Street.
Read moreBRUXELLES
Located near the overpass at the intersection of the Bucharest – Ploiești Road and the Capital’s ring road.
Read moreION I.C. BRĂTIANU
At the intersection of Calea Bucureștilor and Zborului Street in Otopeni.
Read moreAEROPORT OTOPENI
Under the roadway in front of Otopeni “Henri Coandă” International Airport, near the parking area adjacent to the Departures terminal and the exit routes from the Arrivals terminal.
Read more