Metrorex announces updated information on the extension of traffic restrictions for works on M6 Metro Line, South Section, 1 Mai – Tokyo

For execution activities in the framework of the contract “Bucharest International Airport Rail Access Link Project (Metro Line 6. 1 Mai-Otopeni). Design and Build – Civil Works for Lot 1.1: 1 Mai-Tokyo”, METROREX announces the extension of the traffic restrictions on the future alignment of the M6 Metro Line, South Section.

According to the Opinions renewed by the relevant authorities, traffic in the following areas is restricted as follows:

– in the 1 Mai area, at night, traffic is closed from 10:00 p.m. to 06:00 a.m., on Carpați, Mircești and Caransebeș streets, except for residents and public transportation, during the execution of the works related to the project. The traffic participants are asked to use during this time the alternative routes around the works area (via Pajurei Street, Jiului Street, towards Poligrafiei Boulevard), according to the road signs installed from the intersection of Bucureștii Noi Blvd. / Șoseaua Chitilei / Calea Griviței;

– in the area 1 Mai – Pajura, traffic restrictions are extended until 30.09.2025;

– in the Pajura area, the traffic restrictions are extended for the entire period of the building permit, no. 80/12.12.2023, issued by the Ministry of Transport, until March 22, 2027;

– in the areas Pajura – Romexpo – Piața Presei Libere, the restrictions are extended until 30.09.2025;

– in the Gara Băneasa area, the restrictions are extended until 31.01.2025;

– for the future 1 Mai, Aeroport Băneasa and Tokyo stations, the extension Opinions are in the process of being issued, and we will come back with updated information when we receive the decision from the relevant authorities.

Metrorex thanks all traffic participants on the above-mentioned route for their understanding, as well as residents and companies operating in the vicinity of the work zones.

M6 Metro Line will provide a direct connection between Gara de Nord to Otopeni International Airport. It will have a route of 14,2 km and will include 12 metro stations: Pajura, Expoziției, Piața Montreal, Gara Băneasa, Aeroport Băneasa, Tokyo, Washington, Paris, Bruxelles, Otopeni, Ion I. C. Brătianu, Aeroport Otopeni.

Bucharest International Airport Rail Access Link Project (Metro Line 6. 1 Mai – Otopeni) is a project of public utility, of national interest, according to Government Decision no. 496/2017, with subsequent amendments and additions, which ensures the mobility needs of people through the development of the Trans-European Transport Network.

The works for the Design and Build – Civil Works for Lot 1.1: 1 Mai – Tokyo are financed by PNRR. Financed by the European Union – NextGenerationEU.