1 Mai Station

It is located near the existing 1 MAI metro station on Calea Griviței and serves as the junction between M6 Metro Line and M4 Metro Line. The construction site is 144 m long and up to 15 m wide.

Structural monitoring

The measurements carried out so far confirm that the integrity of the buildings is within normal parameters.

Progress of works

  • September 2026: work for the junction with M4 Metro Line is continuing, relocation of the unplanned utilities and the components needed for the junction. 32 plastic piles were made on Line 1 South and 330 meters of guide beam were made on Line 2 North. Implementation percentage of civil works: 55% for Line 1 and 51% for Line 2.
  • August 2026: work for the junction with M4 Metro Line is continuing, relocation of the unplanned utilities and the components needed for the junction. 31 diaphragm walls were made on Line 2 North. Implementation percentage of civil works: 51% for Line 1 and 47% for Line 2.
  • July 2026: work for the junction with M4 Metro Line is continuing, relocation of the unplanned utilities and the components needed for the junction. 99 meters of guide beam and 15 diaphragm walls were made on Line 1 South, 248 meters of guide beam on Line 2 North. Over 8,000 cubic meters of concrete poured. Implementation percentage of civil works: 46% for Line 1 and 47% for Line 2.
  • June 2026: work for the junction with M4 Metro Line is continuing, relocation of the unplanned utilities and the components needed for the junction. 99 meters of guide beam and 12 diaphragm walls were made on Line 1 South and 203 meters of guide beam and 31 diaphragm walls were made on Line 2 North. Over 3,300 cubic meters excavated and over 7,400 cubic meters of concrete poured. Implementation percentage of civil works: 45% for Line 1 and 41% for Line 2.
  • May 2026: work is underway for the junction with M4 Metro Line, (relocation of the unplanned utilities and the components needed for the junction). 4 diaphragm walls were built on Line 1 South and 31 diaphragm walls on Line 2 North. 3,300 cubic meters excavated and 191 cubic meters of concrete poured. Implementation percentage of civil works: 36%.
  • April 2026: relocation of the unplanned utilities and the components needed for the junction with M4 Metro Line. Implementation percentage of civil works: 34%.
  • March 2026: relocation of the unplanned utilities and the components needed for the junction with M4 Metro Line. Implementation percentage of civil works: 33%.
  • February 2026: relocation of the unplanned utilities and the components needed for the junction with M4 Metro Line. 248 meters of guide beam and 31 diaphragm walls were executed for the Joint Gallery with M4, Linia 2 and over 190 cubic meters of concrete were poured. Implementation percentage of civil works: 31%.
  • January 2026: relocation of the unplanned utilities and the components needed for the junction with M4 Metro Line. 195 m of guide beam and 26 diaphragm walls were executed for Line 2 North and 60 cubic meters of concrete were poured. Implementation percentage of civil works: 30,1%.
  • December 2025: A Retrospective of the Year 2025 https://youtu.be/ieKd0B_EEyc?si=nJ5ukuq3udIhmtf_
  • November 2025: execution of the relocation of the unplanned utilities and the components needed for the junction with M4 Metro Line. 155 meters of guide beam, 14 diaphragm walls for Line 2 North were executed and 53 cubic meters of concrete were poured. Implementation percentage of civil works: 22%.
  • October 2025: the planned utilities have been relocated, and work is underway to relocate the unplanned utilities and install the components needed for the junction with M4 Metro Line. Implementation percentage of civil works: 17%.
  • September 2025: work on relocating utilities. Implementation percentage of civil works: 6% for Line 1 and 17% for Line 2.
  • August 2025:130 m of guide beam were installed, while work on relocating utilities continues. Implementation percentage of civil works: 4% for Line 1 and 13% for Line 2.
  • July 2025: work on relocating utilities.
  • June 2025: work on relocating utilities.